Project : Al Bayt Stadium
Client : Supreme Committee.
Consultant : KEO
Contractor : GEIC JV
Subcontractor : L&P JV
GSAS Typology : GSAS v2.1 Sports
Target Rating : 4-Stars
Certification Status : LOC awarded
Scope : Conserve has been appointed by M/s Leonardo Contracting to perform GSAS Construction stage documentation for specific MEP criteria and Performed Stress & Structural Analysis for Entire Stadium chilled water Piping & Fire Fighting piping.

Description

Performed Stress Analysis for entire chilled water supply and returnlines inside the ETS Room. Performed Stress Analysis for entire chilled water supply and return lines inside the whole stadium along with Risers. Performed stress analysis for Firefighting piping for entire stadium. Preparation of load data sheet for all the rigid supports and anchor locations. Support analysis of entire piping network.